The plant is located inland, approximately 40 km west of Muscat in an industrial area. It consists of eight Frame 9E gas turbines installed in four phases between 1984 and 2000. Al Rusail’s primary fuel is natural gas supplied by MEM, but diesel oil is also stored on site to serve as a backup fuel. Power capacity and production are sold to OPWP under the 17-year PPA which ended in September 2021 for 6 gas turbines and March 2022 for 2 gas turbines (Units 7&8). The PPA was extended initially upto 31st October 2022 and again extended upto 31st December 2023. The power plant capacity was initially 665MW (until September 2021), however, after expiration of the PPA for 6 gas turbines, the power capacity is reduced to 186.2 MW.
The combustion turbines are laid out side by side. An overhead travelling crane can access all turbines for maintenance purposes. The generating equipment is outdoor type with the 132 kV Gas Insulated Switchgear (GIS) housed in brick buildings. Underground cable circuits run from the generator step-up transformers to the 132 kV switchgear and then by overhead line to the system at the northern and southern site boundaries. The control room, management offices and administration are housed in one building adjacent to the gatehouse. Spares are housed in a separate building on the site. The Plant is connected to the main interconnected transmission system at 132 kV.
Al Rusail has contracted all O&M activities at the power plant to STOMO.
The Gas Turbines are all the same frame size but have been provided by different suppliers at different times. The EPC Contractors who built Al Rusail units prior to the privatization were MJB / GE / Alstom / BHEL, recognized as some of the world’s leading suppliers of systems, components and services in the generation, transmission and distribution of power. The units at Al Rusail were installed in four phases between 1984 and 2000:
As a result of technology advances over time, the machines have different firing temperatures and spares are therefore not necessarily interchangeable between units.
Generators for GTs 1 to 6 are of Brush (UK) manufacture, for GT 7, Alstom (France) and GT 8, BHEL (India).
GTs 1 to 3 transformers are Bonar Long (UK) manufacture, GTs 4 to 6 Nuova di Legano (Italy), GT 7 i Crompton Greaves (UK) and GT 8 BHEL (India). Following the failure of GT2 transformer in July 2012, it was replaced with a new ABB make transformer.
The 132 kV SF6 switchgear comprises two (2) phases, phase 1 being of GEC (UK) manufacture (12 bays), whilst phase 2 is of Merlin Gerin (France) manufacture, DHT7 (13 bays).
Date | Events |
2 November 2005 | Request for Proposal issued by Tender Board |
26 June 2006 | Bid Submission |
6 December 2006 | Execution of Project Documents |
31 January 2007 | Completion under SPA / Settlement Agreement |
20 February 2007 | Financial Close / Facilities Agreement |
30 September 2021 | Expiry of Phase 1 and Phase 2 (GT1 to GT6) Power Purchase Agreement. Available Capasity - 186.2 |
31 March 2021 | Expiry of Phase 3 (GT7 & GT8) Power Purchase Agreement. |
31 October 2022 | Expiry of Power Purchase Agreement Extension for Phase 3 (GT7 & GT8) |
31 December 2023 | Expiry of Power Purchase Agreement Extension for Phase 3 (GT7 & GT8) |